Technip installs HRD process platform for ONGC using Unideck system

February 26, 2015

PARIS -- Technip has successfully installed the HRD process platform for Oil and Natural Gas Corporation Limited (ONGC), using its proprietary Unideck integrated topside float over installation system for the first time in Indian waters.

The unique feature of this installation method is that it performs the integrated production deck installation in a single operation, thus saving installation time and lowering risks compared to some other traditional methodologies of multiple lifts of smaller modules.

The topsides were designed by Technip in India for the floatover installation, using Technip's proprietary Unideck integrated deck installation system, with the support of Technip in France. Leveraging its expertise and technological know-how, Technip in France ensured the flawless execution of the float over operations.

The HRD project started in 2013, when Technip, in a consortium with AFCONS Infrastructure and TH Heavy Engineering Berhad, was awarded the HRD process platform contract by ONGC.

Samik Mukherjee, Country Head and Managing Director of Technip in India, commented, "It is a moment of pride for Technip in India to witness the installation of approximately 8,200 metric tons integrated production deck onto the Heera field for our client ONGC. The HRD platform will help in increasing field exploration and development activities, thus improving domestic hydrocarbon production."