An extensive, complex conversion of Heerema Marine Contractors’ semi-submersible crane vessel, Balder, into a multipurpose deepwater construction vessel (MDCV) has been successfully completed, after more than 1.2 million man-hours were spent on this project.
After almost 11 months in the Verolme Botlek offshore / ship repair yard’s 405-m-long (1,329-ft), 90-m-wide (295-ft) dry dock, the Balder left on the night of Nov. 10, 2001, and was towed to the deepwater basin in the Caland canal. There, seven thrusters were mounted beneath the floaters. Following completion of this work, the Balder started sea trials. The departure brought to a successful conclusion the largest conversion project ever carried out by this yard. Major conversion programs had previously been carried out on the Petrobrás XXIII semi-submersible drilling rig and the semi-submersible crane vessel Saipem 7000. Conversion of the Balder was bigger than either one of these projects, in terms of both size and complexity. One special feature of the Balder conversion was that three major project components were simultaneously handled. These included installation of a complete dynamic positioning package, implementation of a lifetime enhancement project and installation of facilities for receiving the 120-m-high (394-ft) pipe-laying tower, which weighed 2,300 t. Considerable extra work also had to be carried out. Thanks to sound preparations and a solid project organization, all work was completed on time. In terms of engineering, manufacture, installation, commissioning and hand-over, all work was completed according to a strict timetable. Even in the peak period, when there were more than 1,100 people working on board the Balder at any one time, everything ran smoothly. Thus, the Balder was released from dock on the date agreed with Heerema, and the official re-delivery protocol was signed on Jan. 11, 2002. Heerema had the Balder converted to permit the vessel to take on a key role as a multipurpose construction vessel in the growing deepwater installation market. In its new configuration as an MDCV, the Balder will be put to work for the foreseeable future in the Gulf of Mexico. |
- Mixed outlook for activity on the UK Continental Shelf (December 2023)
- X80 heavy wall pipe solutions for deep/ultra-deepwater field developments in mild sour environment (November 2023)
- Wellbore seal control and monitoring enhance deepwater MPD operations (October 2023)
- Novel approaches to deepwater steel catenary production riser life extension benefit ESG (September 2023)
- Advancing casing drilling to deepwater: Rethinking top hole well construction (August 2023)
- Oil States’ Taylor sees pick-up in OFS business in deepwater and international sectors (June 2023)
- Applying ultra-deep LWD resistivity technology successfully in a SAGD operation (May 2019)
- Adoption of wireless intelligent completions advances (May 2019)
- Majors double down as takeaway crunch eases (April 2019)
- What’s new in well logging and formation evaluation (April 2019)
- Qualification of a 20,000-psi subsea BOP: A collaborative approach (February 2019)
- ConocoPhillips’ Greg Leveille sees rapid trajectory of technical advancement continuing (February 2019)