MOSCOW -- Lukoil has completed the construction and commissioning of the first well at the Phase 2 of Vladimir Filanovsky field in the Caspian Sea.

​This is a production single bore horizontal well with the measured depth of 3.5 km. The horizontal section of the well is 1.2 km. The initial well flow reached 2,400 tonnes of oil per day. As a result, the daily oil production at the field increased to 16,800 thousand tonnes.  

As of today, the company started to drill an injection well. Further execution of the drilling program at the Phase 2 of the field's development will allow to stabilize production at the designed plateau of 6 million tonnes on an annualized basis. 