Emerald Bay begins Kuhn 4 completion operations ahead of schedule

11/10/2017

CALGARY -- Emerald Bay Energy Inc. has announced that completion operations have begun on the Kuhn 4 well at the Company’s Wooden Horse play in South Texas.  

The Company was able to secure services ahead of the November 20th scheduled date and equipment is now being moved on location.  Kuhn 4 will initially be completed in the Buda formation.  The Buda completion operations will take approximately 4-5 days with the production testing phase to begin immediately thereafter as flow lines are in place to the Company’s tank battery.  The production testing phase will take approximately 2-4 weeks. 

Following the Buda formation testing, the Company will move up hole to begin testing the Austin Chalk formation. The Company will update results in the coming days and weeks.