Premier Oil reports arrival of BW Catcher FPSO

10/23/2017

LONDON -- The BW Catcher Floating Production Storage and Offloading (FPSO) vessel arrived at Catcher field on Wednesday, Oct. 18. The hook up of the Submerged Turret Production (STP) buoy mooring system was completed on Oct. 19, with the vessel successfully completing a rotation test around the buoy on the Oct. 20. The final pull-in of the risers and umbilicals is now underway and commissioning activities have also commenced in parallel. Delivery of first oil remains on schedule by the end of the year.