Vallourec to double connection testing capacity with expansion

BOULOGNE-BILLANCOURT, France -- Vallourec has announced its decision to expand its VAM Connection Technology Center in Aulnoye-Aymeries, France, to double its testing capacity. The center currently employs 160 people, who develop VAM tubes and connections to meet the increasing complexity of drilling operations. Amounting to approximately $68.5 million, this investment will result in the creation of 95 jobs by 2016.

The project to expand the testing center in Aulnoye-Aymeries will occur in two stages. Preparation of receiving areas for the new test equipment in existing buildings at the site will begin in first-quarter 2014, and the first additional testing capacities should be operational by 2015.All VAM development and testing capabilities will then be transferred in 2017 to a new building, to be constructed near the existing center. The new, 9,000-sq-m testing facility will be divided into four zones: machining (mechanical metalworking), surface treatment, sample preparation and testing.

The Aulnoye-Aymeries center is one of Vallourec' s three VAM connection test centers, the other two being located in the U.S. and Indonesia. Vallourec plans the construction of a fourth VAM connection testing center in Brazil by 2015.

01/23/2014

 

Bookmark and Share


WO DATA HUB

EngineeringTablesIcon-Large

Engineering Data Tables

World Oil's specialized upstream Engineering Data Tables featuring the Drill Bit Classifier, Tubing Tables and more. Get Total Access today.

WO SUPPLEMENTS

2013 Fracturing Technology

2013 Fracturing Technology

MEDIA CENTER

By Digital Publisher

Drill Bit Classifier World Oil published its renowned Drill Bit Classifier in September 2013. The Drill Bit Classifier is a comprehensive listing of major manufacturers' d...

ENERGY EVENTS